Rebuilding a Fire-Resilient Church

Morinville, AB
From arsoned ruins to a fire-resistant, durable sanctuary, Whitson stepped in to deliver a project that balanced safety and quality—ahead of schedule and on time for the community to celebrate.
Location

Morinville, AB

Project Type

Building Replacement

Status

Complete

Construction Award

$8M

Start Date

2024

Completion

2025

Project Overview

Reinforcing A Fire-Resistant Church Project

Key aspects of the project included structural construction with fire-resistant materials, exterior concrete and siding work, and integration of specialized finishes such as stained glass and A/V systems.

Construction took nearly 18 months—finished ahead of schedule—allowing the Dedication Ceremony to go off flawlessly and the church to welcome its first Christmas congregation in years.

Project Challenges

Challenges & Innovations

CHALLENGE 01

Schedule Management

The project faced over 45 change orders, requiring careful coordination to meet the client’s fixed opening date. Many trades, including client-hired subcontractors, needed close oversight to maintain progress.

CHALLENGE 02

Site Access

Saturated soil conditions in spring and summer limited equipment mobility. Rig mats were installed to maintain site access, preventing delays to exterior work.

CHALLENGE 03

Subcontractor Sequencing

The siding scope extended beyond the original estimate. Work was temporarily paused to prioritize exterior concrete before winter, then resumed under full scaffolding, ensuring deadlines were met despite subcontractor delays.

CHALLENGE 04

Material Compliance

A void form exceeded compressive strength specifications. Additional manpower was deployed to correct it within three days at net zero cost, as overestimated material pickup offset rework expenses.

Project Outcomes

The Results

Our Work

Featured Projects

Scroll to Top